← Back to East Riding of Yorkshire Council
Status
Pending Consideration
Renewable energy
Summary
49.99MW ground-mounted solar farm with substations, cabling, fencing, tracks; temporary 40-year duration.
Full Proposal
Installation of a solar farm comprising ground mounted solar PV panels with an installed capacity of 49.99MW AC including mounting system, transformer substations, underground cabling, fencing, CCTV, internal tracks and associated infrastructure, landscaping, biodiversity net gain and environmental enhancements for a temporary period of 40 years
Documents
. BEVERLEY TOWN COUNCIL
Consultee Comment
. BUILDING CONSERVATION
Consultee Comment
. COUNTRYSIDE ACCESS
Consultee Comment
. HIGHWAY DEVELOPMENT MANAGEMENT
Consultee Comment
. HUMBER HISTORIC ENVIRONMENT RECORD
Consultee Comment
. LAND DRAINAGE
Consultee Comment
. LLFA - LEAD LOCAL FLOOD AUTHORITY
Consultee Comment
. NATURE CONSERVATION OFFICER
Consultee Comment
. TICKTON & ROUTH PARISH COUNCIL
Consultee Comment
ACTIVE TRAVEL ENGLAND
Consultee Comment
AGRICULTURAL QUALITY REPORT
Supporting Documents
ALC REVIEW
Consultee Comment
APPLICATION FORM
Application Form
ARBORICULTURAL SURVEY
Supporting Documents
ARBORICULTURAL SURVEY - TREE PROTECTION PLAN
Plans
ARCHAEOLOGY DESK-BASED ASSESSMENT AND HERITAGE STATEMENT
Supporting Documents
BEVERLEY AND NORTH HOLDERNESS DRAINAGE BOARD
Consultee Comment
BIODIVERSITY NET GAIN - METRIC
Supporting Documents
BIODIVERSITY NET GAIN - STATEMENT
Supporting Documents
COMMUNITY INFRASTRUCTURE LEVY - CIL - FORM 1
Supporting Documents
CONSTRUCTION TRAFFIC MANAGEMENT PLAN
Supporting Documents
COVERING LETTER
Supporting Documents
COVERING LETTER RE. UPDATES
Supporting Documents
CTMP APPENDIX D (SWEPT PATHS)
Supporting Documents
DESIGN CODE COMPLIANCE CHECKLIST
Supporting Documents
DESIGN, ACCESS AND PLANNING STATEMENT
Supporting Documents
ECOLOGICAL ASSESSMENT REPORT
Supporting Documents
ENVIRONMENT AGENCY
Consultee Comment
ENVIRONMENT AGENCY
Consultee Comment
ENVIRONMENTAL CONTROL
Consultee Comment
FLOOD RISK ASSESSMENT
Supporting Documents
FLOOD RISK ASSESSMENT (REVISED)
Supporting Documents
GEO-PHYSICAL INVESTIGATION
Supporting Documents
GLINT AND GLARE STUDY
Supporting Documents
HERITAGE STATEMENT
Supporting Documents
HUMBERSIDE FIRE AND RESCUE
Consultee Comment
INWARD INVESTMENT
Consultee Comment
LANDSCAPE AND VISUAL APPRAISAL - PART 1 OF 5
Supporting Documents
LANDSCAPE AND VISUAL APPRAISAL - PART 2 OF 5
Supporting Documents
LANDSCAPE AND VISUAL APPRAISAL - PART 3 OF 5
Supporting Documents
LANDSCAPE AND VISUAL APPRAISAL - PART 4 OF 5
Supporting Documents
LANDSCAPE AND VISUAL APPRAISAL - PART 5 OF 5
Supporting Documents
LANDSCAPE MASTERPLAN
Plans
LANDSCAPE MASTERPLAN - SHEET 1 OF 5
Plans
LANDSCAPE MASTERPLAN - SHEET 2 OF 5
Plans
LANDSCAPE MASTERPLAN - SHEET 3 OF 5
Plans
LANDSCAPE MASTERPLAN - SHEET 4 OF 5
Plans
LANDSCAPE MASTERPLAN - SHEET 5 OF 5
Plans
LEMP
Supporting Documents
LOCATION PLAN
Supporting Documents
LOCATION PLAN (SUPERSEDED)
Plans
LOCATION PLAN (SUPERSEDED)
Plans
LVA REVIEW FOR ERYC
Consultee Comment
MR PETER NORMAN(FULL)
Public Comment
MRS TRACY ROKAHR
Consultee Comment
MS GEORGINA PUGH(FULL)
Public Comment
MS JILL BURDALL(FULL)
Public Comment
MS SASHA JOWETT GHENT(FULL)
Public Comment
NATIONAL GRID
Public Comment
NATIONAL GRID
Consultee Comment
NATURAL ENGLAND
Consultee Comment
NOISE IMPACT ASSESSMENT
Supporting Documents
NORTHERN GAS
Consultee Comment
NORTHERN GAS
Consultee Comment
NORTHERN GAS NETWORKS
Consultee Comment
NORTHERN GAS PIPELINE
Supporting Documents
PROPOSED CCTV POLE AND ACCESS TRACK SECTIONS
Plans
PROPOSED COMPOUND - ELEVATIONS AND FLOOR PLAN
Plans
PROPOSED COMPOUND - LAYOUT
Plans
PROPOSED PERIMETER FENCING AND INTERNAL GATES - ELEVATIONS
Plans
PROPOSED SERVICE TRENCHES
Plans
PROPOSED SITE BLOCK PLAN - 1 OF 3 (SUPERSEDED)
Plans
PROPOSED SITE BLOCK PLAN - 2 OF 3 (SUPERSEDED)
Plans
PROPOSED SITE BLOCK PLAN - 3 OF 3 (SUPERSEDED)
Plans
PROPOSED SITE BLOCK PLAN - WHOLE SITE (SUPERSEDED)
Plans
PROPOSED SOLAR ARRAY - ELEVATIONS AND PLAN VIEW
Plans
PROPOSED SPARES CONTAINER - ELEVATIONS
Plans
PROPOSED TRANSFORMER SUBSTATION - ELEVATIONS AND PLAN
Plans
SITE BLOCK PLAN (REVISED)
Supporting Documents
SITE BLOCK PLAN (REVISED)
Supporting Documents
SITE BLOCK PLAN (REVISED)
Supporting Documents
SITE BLOCK PLAN (REVISED)
Supporting Documents
SITE NOTICE LOCATIONS WAWNE & THEARNE
Site Notice
SITE NOTICE LOCATIONS WEEL
Site Notice
SITE SELECTION REPORT
Supporting Documents
STATEMENT OF COMMUNITY INVOLVEMENT
Supporting Documents
TRANSFORMER SUBSTATION
Supporting Documents
TRANSPORT STATEMENT
Supporting Documents
TREE SURVEY REPORT (REVISED)
Supporting Documents
YORKSHIRE WATER
Consultee Comment
Take Action
Make your voice heard. Authorities need to hear from people who support new homes.